CLIENT ASSISTANCE
Please read the below details carefully regarding support given by the Agency. Support agreements are sometimes known as an 'S.L.A' (service level agreement) in the industry. It is important to understand support details to manage expectations before entering into a project.
đ Clients who have undertaken a full project receive a lifetime 20% discounted rate for on call support.
The agency does not provide 'default post project support' or 'random unscheduled support'.
All support is given via approved support channels and support protocols on this page.
AGENCY SUPPORT
Last update: 12-06-24
As stated the agency does not provide 'default post project support' or 'ad hoc support' without booking. Support is provided on these 3 protocols:
The only exception to the above are peroids when the agency is taking holiday peroids and emergency scenarios (outlined below).
Requesting support outside the project management system and not providing all needed information will cause delays.
During the course of a active project (as defined above), unless explicity specified otherwise in writing below are expected turnaround times.
The agency will advise if a request is classed as minor (level 1), medium (level 2) or major (level 3).
For example, if a minor request came in at 5pm on a Friday, it may not be completed until the following Tuesday morning.
Project support requests will be also be weighed up and priortised according to any key deadlines dates in within the signed Schedule B - Statement of Work' contract.
Definition of an 'active project':
The peroid after a contract is signed and deposit paid up to the the date when the Schedule C is signed by both parties.
Please note that support is suspended if a project has entered 'Max Duration' and is consider 'inactive'.
In this case support protocols and support times will no longer apply as the project has become unpaused.
Definition of a 'completed project':
The peroid after Schedule C is signed offed by both parties.
There is no 'default post project' support, unless specified in Schedule B, or a legacy arrangement in place.
This is explicitly outlined in document 'Schedule C'.
After the conclusion of a project, the below options are available.
Only available at the start of a project. This support add-on runs from the project completion date. During this duration core support protocols and project support times apply. Following the conclusion of this peroid 'on call' support will need to be purchased.
Existing clients receive a lifetime 20% discount for 'on call' support bookings. Book using the 'support booking box' on this page. This pins down a specific peroid to work on the requested support.
Emergency scenarios that would require immediate assistance outside of office hours include matters such as:
The steps agreed in the signed 'Schedule of Work' to ensure the Project end date can be reached.
The project end date is the end goal for the project. This can be adjusted depending on arrangements by both the client and the agency. It is a 'soft pause'
The project 'max duration' is the 'hard pause' date extended beyond the end date. The project 'max duration pause' only occurs if the agency has fullfilled it's key deadline date, but the client was unable to fulfil their deadlines resulting in the max duration being exceeded.
We understand and empathise that life will sometimes throw us curve balls and our attention has to be diverted to more important personal matters. As the agency is small and commitments have likely been made to other parties for project start dates, these need to be honoured. The pause on a project is a temporary situation while timelines are put back on track. There is no penalty or loss of commitment, the project will be fulfilled as agreed in the signed documents.
Only in the case that the agency has fullfilled it's key deadline dates, but the client was unable to for a variety of circumstances, the project will need to be temporarily paused.
However if there have been no emergency sitations on the agency side (such as critical illness or bereavement) but it is the agency that have not fullfilled it's key deadline dates - the project pause will not occur. Instead work will continue with an end date mutually agreed on as soon as is possible.
No. It simply means there will need to be some time where project requests and project work will not take place. During this time 'active project' support protocols will not apply. The duration of the pause will depend on agency's other commitments and will range from a minimum of 1 week to several months. The agency will agree 'reactivation' with the client as soon as is possible.
For clients with an active project, you can book a catchup below.
Previous clients can book a discounted single hour session below or alternatively other more extensive support sessions.